We got the hang of how the ICF come together today. In addition we fixed the mistakes that were created from Friday. Also once we got the first and second courses laid we were able to attempt squaring off the corners. We started on the 3rd and 4th courses today. The rebar was put in place but it was no easy task. There was always something in the way to keep it from lying nicely. There is supposed to be more rain tomorrow and the rest of the week will be really cold. The joys of construction! We also wrote some threatening notes to makes sure people do not move the walls that we painstakingly squared off.